Belgian inspectors ordered roughly 300 workers off a nearly finished Google data center in Farciennes, three days after a Virginia judge froze a separate $3 billion campus in Botetourt County. One fight is about water, the other about transparency — and neither site is moving.
- Original source: cryptobriefing.com.
- The source published it on Nov 29, 2026 at 7:35 PM.
- No second outlet has reported it yet. Treat it as a single-source claim.
Inspectors in Belgium's Wallonia region ordered about 300 workers off a Google data center site in Farciennes, near Charleroi, on Thursday. The 30,000 m² facility was close to completion when they arrived. The sticking point: a water-cooling permit.
That permit got a temporary green light in April 2026, then was revoked in August 2026. According to Wallonia's regional government, Google kept building after the amended permit was pulled. The inspection ran November 26-27, 2026, and it followed evidence of compliance issues handed over by Greenpeace Belgium — the environmental group was the tipster that triggered enforcement. Google said it had paused work pending additional guidance and would seek clarity on its compliance obligations in Belgium.
In Virginia, the problem isn't water. On November 23, 2026, a circuit court judge ruled that the performance agreement for Google's planned $3 billion data center in Botetourt County violated the state's Freedom of Information Act, finding county supervisors broke open-government law when they approved the arrangement. Construction there had begun in September 2026; the ruling stopped it, with only limited wind-down work continuing.
Google isn't a newcomer to Belgium — it opened its first European data center in Saint-Ghislain back in 2007, and the country has anchored its European infrastructure since. Water is the flashpoint at Farciennes, where critics point to an existing Google facility that uses about 1 billion liters of water a year. Objections cluster around three things: water extraction, energy use and procedural transparency.
The next formal checkpoint in Belgium is a Council of State hearing on Google's appeal, set for January 7, 2027, which will show whether the company keeps the Farciennes permit or has to rework how the site is cooled. Virginia hearings land in early 2027, where the question is whether Botetourt County reruns its approval process in the open.
TopicsGoogle · Greenpeace Belgium · Wallonia · Botetourt County · Farciennes · Council of State · Saint-Ghislain · Virginia
Source: cryptobriefing.com
Written by AI from verified reporting.
More stories
- Tech & AI cbsnews.com Caught by @kylebrennanFitzpatrick: AI Needs Global Guardrails or World Heads to a 'Very, Very Dangerous Place'
- Tech & AI cryptobriefing.com 3 viewsNvidia freezes Southeast Asia shipments as US export rules bite
- Tech & AI cryptobriefing.comMicron and SK Hynix hit 80% margins as AI memory stays sold out
- Tech & AI cryptobriefing.com Caught by @mr_ken007 4 viewsNvidia makes neoclouds hand over client lists before any GPU ships